Bio-Cremation (Alkaline Hydrolysis) Sewer Use Advice
Provided analysis of impacts of alkaline hydrolysis waste on local wastewater collection and treatment system and recommendations on wastewater pre-treatment, discharge agreement, and treatment plant management.
City of Markham Pump Station Condition Assessment
Undertook field investigations of four pumping stations and collected assessments by a mobile device and compiled a photo log for storage in a database. Prepared reports identifying the condition, life-cycle, and expected replacement cost of stations.
Brittany Drive Pump Station Reconstruction
Provided functional and detailed designs for a new pump station containing three pumps. Wrote specifications, constructability report, and temporary water service memorandum.
Richmond Pump Station and Reservoir Construction
Participated in communal water system construction by creating inventory, and finalizing deficiency list. Inspected testing and construction progress.
Britannia Watermain Repair
Inspected carbon fiber pipe relining, and prepared progress payment.
Carlsbad Watermain Construction
Inspected 2-km horizontal directional drilling for watermain installation.
East End Culverts Replacement
Inspected culverts installation.